77% of Australia's $70B Data-Centre Bet Has No Power
77% of Australia's $70B Data-Centre Bet Has No Power By Daniel Rao · October 24, 2026 Australia wants to be the AI capital of the Asia-Pacific. It has a plan, billions of dollars in announced investment, and the backing of governments desperate to look like winners in the AI race. There is just one small problem: most of its data centres can't plug in. A Bloomberg review of company disclosures, published October 23, found that more than three-quarters of the 40-plus large data centres planned or under construction around Sydney and Melbourne — representing more than A$100 billion (US$70 billion) of projected investment — have not publicly confirmed they have secured electricity supply or grid connections. Just 23% have. In Sydney, seven of 28 active projects have confirmed power. In Melbourne, the figure drops to three of 15. That isn't a pipeline. That's a wish list with a power cable missing. The story gets worse from there. While developers were announcing gigaw...