Data Centres Now Face $5M-a-Day Fines for Opening Late
Data Centres Now Face $5M-a-Day Fines for Opening Late
By Daniel Rao | 26 October 2026
There is a new number doing the rounds in the data-centre business, and it tells you everything about where the AI boom actually stands. It is not a chip price, not a valuation, not a gigawatt figure. It is $5 million. Per day. That is what tenants building the AI boom are now demanding from developers for every day a data centre opens late — up from about $1 million as recently as this spring, according to The Information.
Read that twice, because the fivefold jump is the story. In six months, lateness went from an annoyance you could price into a contract to a penalty that can eat a developer alive. And the people writing these clauses are not bluffing for fun. They are writing them because they expect the dates to slip.
We checked the obvious question first: is this a real shift, or one angry tenant? The Information's reporting, carried Sunday by WebProNews, AI Weekly, BeInCrypto and others, traces it to the insurance market — which is where you go when a risk gets too big to carry yourself. Marsh, the broker, had already built a bespoke "delay-in-delivery" policy this spring for a developer whose tenant wanted $1 million a day if the first phase of a gigawatt-scale campus missed its date. Within months, the ask in fresh deals had moved to $5 million and up. Insurers do not invent products for imaginary problems.
The tenants have the leverage, and they know it
Why would a developer sign something like this? Because the tenant on the other side of the table is a hyperscaler or an AI lab, and there is a queue of developers behind them who will. The leverage sits entirely with the buyer of capacity. Every developer wants a hyperscaler on a long-term lease; no hyperscaler needs any particular developer. So the penalty clause is where that imbalance shows up in print.
It also shows up in the small print of deals that are already signed. SoftBank-backed SB Energy is building a 10-gigawatt campus in Ohio for OpenAI, and the Wall Street Journal, reading SB Energy's IPO filing, found the ladder: OpenAI gets one free day of base rent for every day of delay, and that doubles to two free days once the delay passes 90 days. Run the maths on a full year late and you land at 640 days of free rent — nearly two years of income handed back for one year of slippage. We asked ourselves whether that number could really be right, and the arithmetic checks: 90 days at one-for-one, then 275 days at two-for-one, is 640. It is not a typo. It is a contract.
There is a second sting in the SB Energy deal that rarely makes the headlines. The Ohio campus relies on a 9.2-gigawatt gas plant that SB Energy will not own or run. So the tenant's rent holiday is triggered by a power plant the developer does not control. That is the AI buildout in one sentence: enormous promises, assembled from parts nobody fully controls, on timelines nobody can guarantee.

Photo: Server racks in a data centre. The $5M-a-day clauses are priced on rooms like this sitting empty past their promised date. Photo: Carl Lender, Wikimedia Commons, CC BY 2.0.
Goldman expects half the pipeline to miss
The tenants are not being paranoid. Goldman Sachs Research, working from Aterio's facility-level tracking, estimated in May that only about 60% of US data-centre capacity scheduled for the next year would come online on time — and only about half of what is slated for the next two years. Historically, about 72% of capacity scheduled for the following four quarters opened when promised. In other words, the industry is getting worse at hitting its own dates, not better, even as the dates get more expensive.
Goldman's analysts — Hongcen Wei, Daan Struyven and Samantha Dart — named supply-chain and labour shortages as the most common causes, and put a typical build at 18 to 24 months once permits are secured. Even after applying those haircuts, they still expected 11.5 gigawatts of new capacity in the final three quarters of 2026, following 2.2 gigawatts in the first quarter. And they flagged reliability risks in the Mid-Atlantic, Mid-Continent and Northwest power markets, where planned generation trails incoming demand — regions that, in Goldman's words, may end up turning some future data centres away.
That last point is worth sitting with. The constraint is no longer money, and it is no longer chips. It is the grid. Microsoft walked away from its agreement for Nscale's planned site in Loughton, Essex, after grid delays pushed electricity availability into the 2030s. Oracle, going the other direction, started trucking compressed natural gas to sites in Utah and Texas, paying about four times the cost of piped supply to keep projects moving while pipelines catch up. When a company starts trucking its own gas, the bottleneck is not theoretical. Australia has gone further still, voting to slow AI down — and make data centres pay for the grid they use.

Photo: High-voltage transmission lines in Auburn, Washington. Power, not chips, is now the binding constraint on AI data centres. Photo: Ron Clausen, Wikimedia Commons, CC0.
The insurers have already priced the panic
Marsh's Mike Mathews, who runs the broker's global digital infrastructure practice, put the underwriting problem in unusually plain language at a press webinar in March: "You have a $4 billion data centre with $10 billion worth of equipment in a single site facility. So, the size and scale is the challenge." A single building, $14 billion of exposure, one missed date. That is why the firm's Nimbus facility — launched in June 2025 for large data-centre construction, starting at up to $1 billion in construction all-risks limits and $365 million for delay in start-up — had its limits raised in January to as much as $2.7 billion, including delay-in-start-up and business interruption cover, across the UK, US, Canada, Europe, Australia and New Zealand.
The newer product goes after a different bill. Nimbus covers the developer's own losses from a delay. The policy Mathews' team arranged this spring covers the late fee the developer owes its tenant — the $5 million a day itself. When insurers start selling cover for the penalty clause, the penalty clause has become a line item in the industry's cost structure. It is no longer a negotiating tactic. It is a risk class.
And the pipeline behind those policies keeps growing. Goldman forecasts US data-centre power demand rising from 31 gigawatts in 2025 to 66 gigawatts in 2027. On Aterio's schedules, developers are due to add 36.3 gigawatts of US capacity in 2027 — more than four times the 8.5 gigawatts that actually came online in 2025. If only half of that arrives on time, as Goldman expects, then the $5 million clauses are not edge cases. They are the central financial fact of the 2027 buildout.
Oracle already reached for the legal escape hatch
You can see the same fear from the tenant side. Oracle sent a force majeure notice in September on its Project Jupiter campus in New Mexico — a legal claim of uncontrollable events that preserves its right to defer rent if power delays affect the planned 2028 opening. Oracle says the project is on schedule. Its landlord, Blue Owl Capital, played the move down, saying "this notice does not change the financial commitments to this multi-year project." Both things can be true at once: the project can be on schedule, and the tenant can still want the paperwork in place for the day it is not. That is what force majeure notices are for. They are not predictions. They are insurance, filed in advance, in public.
New Mexico regulators rule on the campus air permit by 23 November. Watch that date. Permits are the quiet part of every data-centre timeline — the 18 to 24 months Goldman cites starts only once permits are secured, and the permit itself is where local opposition, environmental review and grid-connection queues all collide.
SB Energy is the cautionary tale in real time
If you want to see what happens when the market stops believing the timeline, look at SB Energy itself. In September it postponed a planned $5 billion IPO after buyers pushed back on a $50 billion valuation. None of its data centres is open. It booked $139 million in revenue in the first half of the year — about $278 million annualised — against that $50 billion ask. It may now list in December or next year. The market did not reject the AI story. It rejected the price of a story with no operating assets and a 640-day rent holiday hanging over its flagship campus.
Markets have punished late builds before. In November 2025, CoreWeave shares fell about 16% after the company blamed one developer's delay for a weak forecast. CoreWeave's bonds were yielding close to 15% earlier this month, and its quarterly interest expense reached $640 million in the June quarter, up from $267 million a year earlier, on roughly $50 billion of debt. The chain is short and brutal: developer misses a date, tenant's forecast misses, lender reprices the debt, and suddenly the next campus costs more to finance — which makes the next date harder to hit.
Whether this is discipline or a death spiral
So is the $5 million clause a sign of health or sickness? Honestly, it is both, and anyone telling you it is only one is selling something.
The healthy reading: this is how a maturing industry prices risk. Tenants who lose real revenue for every day without capacity should charge for it. Developers who cannot hit dates should pay for it. Insurers who can price it should sell cover for it. That is a market working, not failing. Broadcom chief Hock Tan's warning that some AI investors act like they are "in a casino" is the counterweight here — not every dollar in this boom is disciplined, but the penalty clause is at least an attempt at discipline.
The sick reading: the clause exists because everyone privately expects failure. When half the pipeline is forecast to miss, and the penalty for missing is $5 million a day, and the insurer's answer is a new product line, you have built a system that transfers risk to the party least able to absorb it — the developer — while the tenant keeps the upside and the lender reprices at the first wobble. Elon Musk said it out loud on Sunday, in the same weekend this reporting landed: debt markets have "almost entirely shut off" for companies without substantial revenue outside AI data centres, and 200-plus neoclouds face "guppy-level death and consolidation." Our own reporting on Musk's $40 billion GPU borrowing carries the full context, and Gartner's October forecast backs the warning: more than 80% of neocloud providers will cease operating independently by 2030.
The truth, as usual, sits between the two readings and leans toward the second. A $5 million daily penalty does not make a data centre open faster. It makes the developer's balance sheet thinner on the day it opens late. And in a year when half the pipeline is expected to be late, that is a lot of thin balance sheets arriving at once.
BlackRock chief Larry Fink warned that halting data-centre construction would push the US into recession. He may be right about the direction and wrong about the mechanism. Nobody needs to halt construction for this boom to hurt. All it takes is for construction to arrive late, at $5 million a day, on contracts written by tenants who knew it would.
Data-centre late fees: your questions answered
What exactly are tenants demanding?
Tenants negotiating new AI data-centre leases are asking developers for more than $5 million per day in penalties if power and facilities are not delivered on time, up from about $1 million a day this spring, according to The Information. These are demands in negotiations, not settled terms in every deal — the distinction matters, and the reporting is careful about it.
Why do tenants expect delays?
Because delays are the norm, not the exception. Goldman Sachs expects only about 60% of US capacity scheduled for the next year, and about half of next-two-years capacity, to open on time, with supply-chain and labour shortages the most common causes and a typical build taking 18 to 24 months once permits are secured.
What does the SB Energy–OpenAI deal actually say?
Under the Ohio campus deal, as reported by the Wall Street Journal from SB Energy's IPO filing, OpenAI receives one free day of base rent per day of delay, doubling to two after 90 days — 640 free days for a full year late. The campus relies on a 9.2-gigawatt gas plant SB Energy will not own or run.
Who pays when a project slips?
First the developer, through the penalty or rent holiday. Then, increasingly, the insurer — Marsh now sells delay-in-delivery cover for the tenant penalty itself. And finally the lender, through repriced debt, as CoreWeave's near-15% bond yields and $640 million quarterly interest bill show.
What should I watch next?
Three dates: New Mexico's air-permit ruling on the Oracle campus by 23 November; whether SB Energy lists in December and at what valuation; and whether the $5 million ask hardens into signed terms or softens as developers push back. If tenants start accepting lower penalties, the panic is easing. If the ask climbs again, it is not.
By Daniel Rao, TechPulse USA. Daniel covers AI infrastructure and the economics of the buildout. TechPulse USA is an independent publication; this article is based on reporting by The Information (via WebProNews, AI Weekly and BeInCrypto relays), Goldman Sachs Research, the Wall Street Journal's reading of SB Energy's IPO filing, and TechCrunch. We checked the 640-day rent-holiday maths ourselves (90 days at one-for-one, plus 275 days at two-for-one) before printing it, and we checked our own archive first: no earlier TechPulse post covers the $5M-a-day clause.
Sources: The Information (25 Oct 2026, via relays); WebProNews, "AI Data Center Tenants Now Want $5 Million a Day When Projects Run Late" (25 Oct 2026); BeInCrypto, "AI Just Put a $5 Million-a-Day Price Tag on Its Biggest Bottleneck" (25 Oct 2026); Goldman Sachs Research, May 2026 data-centre analysis (via WebProNews); Wall Street Journal, SB Energy IPO filing reporting (via BeInCrypto); TechCrunch, Oracle Project Jupiter force majeure (Sept 2026); Business Insurance / Marsh, Nimbus facility (June 2025, Jan 2026).